Wineries
TANK
CHANNEL WRAPPING Utilizing
current technology and quality improvement techniques, Corey Delta
installed channel jackets on eight 100,000 gallon
tanks for a winery located in Healdsburg, California. The channel
jackets were installed by using flexible track travel carriages,
carrying water cooled wire feed track welders, to weld channel
water jackets to the tanks exterior walls. RED
WINE FERMENTATION PROJECT This was a
fast track project for a Sonoma County winery. This
ground up project included excavation work and underground piping,
new concrete slabs, fabrication and installation of structural
steel systems, installation wine tanks and fabrication and installation
of various types of conveyors and piping systems. The press
is being utilized as a common rolling type press which
can accept must from seven different types of wine tanks. This
process will determine which of the tanks will produce the best
product and will assist with future expansion projects. CRUSH
FACILITY INSTALLATION The crush
and truck offloading facility involved numerous vendors and subcontractors
coordinated by Corey Delta, acting as the General Contractor.
Forty percent of the overall cost of our contract involved a mass
excavation and concrete placement to allow for incoming and outgoing
truck traffic. Our self-performed work included the installation
of the dump hopper offloading hoist system, crusher/destemmer,
pomace conveyors and related utility piping. The project was completed
in approximately eight weeks. PRESS
AREA EXPANSION Our main objective
on this fast track project, while maintaining an impeccable safety
record and quality control, was to finish all the necessary improvements
before the harvest. The project included the onsite fabrication
and installation of the 130 long structural steel pipe bridge. Also included
in this project, was the fabrication and installation of over
6,000 of stainless steel wine lines leading into a new bottling
facility. The welding of the pipe was accelerated and quality
was maintained by utilizing orbital welding machines. This project
was completed in fourteen weeks with zero lost time or recordable
incidents expending 14,000 man hours. BOTTLING
LINE INSTALLATION The central
part of the project was the installation of a new Krones Mono
Block Filler Machine; made up of four sections including an infeed
table, a rinser, the filler and a corker. The assembled machine
weighs in excess of 31 tons. With a rated capacity of 345 bottles
per minute for 1.5L size bottles and 550 bottles per minute for
750ml size bottles, it is one of the fastest filler machines and
bottling lines in existence in the world. Other major equipment
installed included: ROTARY
FERMENTER INSTALLATIONS Over a two
year span, Corey Delta, acting as General Contractor, installed
10 new rotary fermenters. The civil, structural framing, equipment
setting, aluminum catwalks, must and utility piping were all installed
utilizing Corey Delta crews. The subcontracted work included electrical,
structural steel and catwalk fabrications. Engineering costs for
this project were minimized with the use of owner/contractor engineering
meetings and the use of plans and specifications from previous
projects at the facility. Any additional engineering requirements
were subcontracted by Corey Delta. This project was installed
simultaneously with additional major upgrades that were all completed
on a fast track schedule before harvest time. |